Tuesday 21 January 2014

Introduction To Unfired Pressure Vessels

Introduction To Unfired Pressure Vessels

Under the Factories and Machinery Act 1967, each unfired pressure vessel must have a valid certificate of fitness (CF) before it can be operated. For this purpose, approval for the design of the unfired pressure vessel has to be obtained in advance from the Department of Occupational Safety and Health (DOSH) before it fabricated, installed or used.

Application for approval of the design may be made by the manufacturing company, installer, supplier or owner of the unfired pressure vessel. Local manufacturers of unfired pressure vessels must register as a manufacturer with the department.

The following are several examples of unfired pressure vessels that require design approval:
  1. Air container
  2. Sterilizer
  3. LPG storage tank
  4. Heat Exchanger
  5. Pressure vessels at the petrochemical plants etc

For further enquiries, please contact the On Duty Officer

Unfired Pressure Vessel Unit,
Industrial Safety Division,
Department of Occupational Safety and Health,
Level 3, Block D3, Complex D,
Federal Government Administrative Centre
62530 Putrajaya

Tel: 603-8886 5342

Fax: 603-8889 2349

Monday 20 January 2014

APPLICATION FOR DESIGN (STEAM BOILER, HOISTING MACHINES, UPV & LIFTS) AND PIPELINE APPROVAL - SKUD V3

APPLICATION FOR DESIGN (STEAM BOILER, HOISTING MACHINES, UPV & LIFTS) AND PIPELINE APPROVAL - SKUD V3
Document Control and Manage System (SKUD) v3 is one of the online services provided by Department of Occupational Safety and Health (DOSH) to facilitate department’s client especially for steam boiler, hoisting machines, unfired pressure vessel (UPV), lifts and pipeline approval design application. This system is developed to be used by Design Section, Industrial Safety Division.

This system is a web-based system whereby it can be accessed through DOSH website. Department’s client can submit their application and documents needed through online at any places that have internet access. Every application submitted will be processed directly through the system by the officer in charge. The client can also check their application status and download the design approval letter through this system anytime and anywhere. This system also provides online payment facility to their client whether to use credit card or FPX facility.

However, the client must ensure the used browser because this system only can be viewed or accessed through Internet Explorer 7 and 8.

For any application, status checking or design approval letter download, please click:

Application for Design (Steam Boiler, Hoisting Machines, UPV & Lifts) and Pipeline Approval - SKUD V3.

For any enquiry regarding to the system, please contact:

i.  En. Zahari bin Hitam
    (E) mzahari@mohr.gov.my
    (T) 03-8886 5075

ii.  En. Mohd Shamsuri bin Khalid
    (E) mshamsuri@mohr.gov.my
    (T) 03-8886 5324

iii.  En. AlMuhaymin bin Abdul Hadi
    (E) almuhaymin@mohr.gov.my

    (T) 03-8886 5309

Wednesday 15 January 2014